The City has relaxed rules for additional dwelling units on single residential erven to encourage gentle densification. Whether you need a planning application depends on your zone, erf size, title conditions and parking.
Which rules apply? Examples and terms on this page (such as the Development Management Scheme and "departures") come from the City of Cape Town. Other Western Cape municipalities apply their own planning by-law and zoning scheme, so names, requirements, fees and timeframes differ.
When you need it in Parow Valley
- Building a garden cottage or flat above the garage
- Converting an outbuilding into a rental unit
- Adding a third dwelling on a larger erf
The process
- 1
Rights check
We confirm whether the extra unit is a primary right for your zone and erf size, or needs consent or departures.
- 2
Title check
We look for 'one dwelling only' conditions in the title deed.
- 3
Application or building plans
If no planning application is needed, you can go straight to building plans; otherwise we lodge the necessary applications first.
Documents usually needed
- Title deed
- Site plan showing the new unit
- Parking layout
Timing
Where only building plans are needed, planning approval is not required. Applications take 2–6 months.
Watch out for
- Additional units are not separately sellable without a sectional title scheme or subdivision
- Services connections may need upgrading
Estimates only. Timeframes are indicative, based on typical City of Cape Town applications, and are not guaranteed. They exclude municipal backlogs, incomplete submissions, objections, appeals, heritage or environmental processes, survey and deeds registration. Municipal fees are set by each municipality's current tariff schedule; professional fees are quoted separately. No outcome or approval is guaranteed; the municipality decides independently. See our disclaimer.